Our Products
MR. JO Floor-SL0.5
System Properties
- Color: Neutral | Factory Pigmented
- Pot life @25°C: 20-40 mins
- Mixing Ratio: 100:50:120 PBW
- Good mechanical properties
- Mixture consistency: Self levelling
- Thickness 0.5mm
- Coverage: 0.8 kg/m2
Applications
- Garage
- Mechanical workshops
- Warehouses
- Parking area
How to use
-
The mixture should be applied on a clean and rough surface. For good results, it is required that the substrate is free from loose particles. Suitable degreasing agent should be used to remove any grease, oil or traces on the surface.
-
Repair the surface if damaged. Allow 2-3 hours for surface of repaired area to dry. Choose a suitable product from Jpoxy’s JO range of Adhesives for repairing.
-
Apply primer for better adhesion on substrate. Allow 4-5 hours for surface of repaired area to dry. Choose a suitable product from Jpoxy’s JO range of Primers.
-
An underlay is suggested if the substrate is badly damaged or is prone to high level of mechanical abrasion. Allow 4-5 hours for surface of repaired area to dry. Choose a suitable product from Jpoxy’s JO range of Underlays.
-
Mix all the three components provided in kit thoroughly for at least 2minutes. Copper mesh is laid and then mix directly poured and spread with the help of trowel.
-
Allow 5-6 hours for surface to dry and 24 hours to achieve full strength.
MR. JO Floor-CRSL0.5
Packaging: 13.5 KG
System Properties
- Color: Neutral | Factory Pigmented
- Pot life @25°C: 20-40 mins
- Mixing Ratio: 100:50:120 PBW
- Self levelling
- Thickness: 0.5mm
- Coverage: 0.8 kg/m2
Applications
- Area prone to chemical spillage
- Laboratory
- Industrial floors
- Area prone to oil spillage
How to use
-
The mixture should be applied on a clean and rough surface. For good results, it is required that the substrate is free from loose particles. Suitable degreasing agent should be used to remove any grease, oil or traces on the surface.
-
Repair the surface if damaged. Allow 2-3 hours for surface of repaired area to dry. Choose a suitable product from Jpoxy’s JO range of Adhesives for repairing.
-
Apply primer for better adhesion on substrate. Allow 4-5 hours for surface of repaired area to dry. Choose a suitable product from Jpoxy’s JO range of Primers.
-
An underlay is suggested if the substrate is badly damaged or is prone to high level of mechanical abrasion. Allow 4-5 hours for surface of repaired area to dry. Choose a suitable product from Jpoxy’s JO range of Underlays.
-
Mix all the three components provided in kit thoroughly for at least 2minutes. Copper mesh is laid and then mix directly poured and spread with the help of trowel.
-
Allow 5-6 hours for surface to dry and 24 hours to achieve full strength.
MR. JO Floor-SL1
Packaging: 15 KG
System Properties
- Color: Neutral | Factory Pigmented
- Pot life @25°C: 20-40 mins
- Mixing Ratio: 100:50:150 PBW
- Good mechanical properties
- Mixture consistency: Self levelling
- Thickness: 1 mm
- Coverage: 1.6 kg/m2
Applications
- Garage
- Mechanical workshops
- Warehouses
- Parking area
How to use
-
The mixture should be applied on a clean and rough surface. For good results, it is required that the substrate is free from loose particles. Suitable degreasing agent should be used to remove any grease, oil or traces on the surface.
-
Repair the surface if damaged. Allow 2-3 hours for surface of repaired area to dry. Choose a suitable product from Jpoxy’s JO range of Adhesives for repairing.
-
Apply primer for better adhesion on substrate. Allow 4-5 hours for surface of repaired area to dry. Choose a suitable product from Jpoxy’s JO range of Primers.
-
An underlay is suggested if the substrate is badly damaged or is prone to high level of mechanical abrasion. Allow 4-5 hours for surface of repaired area to dry. Choose a suitable product from Jpoxy’s JO range of Underlays.
-
Mix all the three components provided in kit thoroughly for at least 2minutes. Copper mesh is laid and then mix directly poured and spread with the help of trowel.
-
Allow 5-6 hours for surface to dry and 24 hours to achieve full strength.
MR. JO Floor-CRSL1
Packaging: 15 KG
System Properties
- Color: Neutral | Factory Pigmented
- Pot life @25°C: 20-40 mins
- Mixing Ratio: 100:50:150 PBW
- Good Chemical resistant
- Mixture consistency: Self levelling
- Thickness: 1 mm
- Coverage: 1.6 kg/m2
Applications
- Area prone to chemical spillage
- Laboratory
- Industrial floors
- Area prone to oil spillage
How to use
-
The mixture should be applied on a clean and rough surface. For good results, it is required that the substrate is free from loose particles. Suitable degreasing agent should be used to remove any grease, oil or traces on the surface.
-
Repair the surface if damaged. Allow 2-3 hours for surface of repaired area to dry. Choose a suitable product from Jpoxy’s JO range of Adhesives for repairing.
-
Apply primer for better adhesion on substrate. Allow 4-5 hours for surface of repaired area to dry. Choose a suitable product from Jpoxy’s JO range of Primers.
-
An underlay is suggested if the substrate is badly damaged or is prone to high level of mechanical abrasion. Allow 4-5 hours for surface of repaired area to dry. Choose a suitable product from Jpoxy’s JO range of Underlays.
-
Mix all the three components provided in kit thoroughly for at least 2minutes. Copper mesh is laid and then mix directly poured and spread with the help of trowel.
-
Allow 5-6 hours for surface to dry and 24 hours to achieve full strength.
MR. JO Floor-SL2
Packaging: 16.5 KG
System Properties
- Color: Neutral | Factory Pigmented
- Pot life @25°C: 20-40 mins
- Mixing Ratio: 100:50:180 PBW
- Good mechanical properties
- Mixture consistency: Self levelling
- Thickness: 2 mm
- Coverage: 3.2 kg/m2
Applications
- Garage
- Mechanical workshops
- Warehouses
- Parking area
How to use
-
The mixture should be applied on a clean and rough surface. For good results, it is required that the substrate is free from loose particles. Suitable degreasing agent should be used to remove any grease, oil or traces on the surface.
-
Repair the surface if damaged. Allow 2-3 hours for surface of repaired area to dry. Choose a suitable product from Jpoxy’s JO range of Adhesives for repairing.
-
Apply primer for better adhesion on substrate. Allow 4-5 hours for surface of repaired area to dry. Choose a suitable product from Jpoxy’s JO range of Primers.
-
An underlay is suggested if the substrate is badly damaged or is prone to high level of mechanical abrasion. Allow 4-5 hours for surface of repaired area to dry. Choose a suitable product from Jpoxy’s JO range of Underlays.
-
Mix all the three components provided in kit thoroughly for at least 2minutes. Copper mesh is laid and then mix directly poured and spread with the help of trowel.
-
Allow 5-6 hours for surface to dry and 24 hours to achieve full strength.
MR. JO Floor-CRSL2
Packaging: 16.5 KG
System Properties
- Color: Neutral | Factory Pigmented
- Pot life @25°C: 20-40 mins
- Mixing Ratio: 100:50:180 PBW
- Good Chemical resistant
- Mixture consistency: Self levelling
- Thickness: 2 mm
- Coverage: 3.2 kg/m2
Applications
- Area prone to chemical spillage
- Laboratory
- Industrial floors
- Area prone to oil spillage
How to use
-
The mixture should be applied on a clean and rough surface. For good results, it is required that the substrate is free from loose particles. Suitable degreasing agent should be used to remove any grease, oil or traces on the surface.
-
Repair the surface if damaged. Allow 2-3 hours for surface of repaired area to dry. Choose a suitable product from Jpoxy’s JO range of Adhesives for repairing.
-
Apply primer for better adhesion on substrate. Allow 4-5 hours for surface of repaired area to dry. Choose a suitable product from Jpoxy’s JO range of Primers.
-
An underlay is suggested if the substrate is badly damaged or is prone to high level of mechanical abrasion. Allow 4-5 hours for surface of repaired area to dry. Choose a suitable product from Jpoxy’s JO range of Underlays.
-
Mix all the three components provided in kit thoroughly for at least 2minutes. Copper mesh is laid and then mix directly poured and spread with the help of trowel.
-
Allow 5-6 hours for surface to dry and 24 hours to achieve full strength.
MR. JO Floor-ASL1
Packaging: 11.25 KG
System Properties
- Color: Pigmented
- Pot life @25°C: 20-40 mins
- Mixing Ratio: 100:50:75 PBW
- Electrostatic dissipating properties
- Mixture consistency: Self levelling
- Mixture consistency: Self levelling
- Thickness: 1 mm
- Coverage: 1.6 kg/m2
Applications
- Data center
- Semiconductor fabrication industry
- Military & aerospace industries
- Antistatic flooring
How to use
-
The mixture should be applied on a clean and rough surface. For good results, it is required that the substrate is free from loose particles. Suitable degreasing agent should be used to remove any grease, oil or traces on the surface.
-
Repair the surface if damaged. Allow 2-3 hours for surface of repaired area to dry. Choose a suitable product from Jpoxy’s JO range of Adhesives for repairing.
-
Apply primer for better adhesion on substrate. Copper mesh is suggested to be laid before applying primer. Allow 4-5 hours for surface of repaired area to dry. Choose a suitable product from Jpoxy’s JO range of Primers. Rub the surface with sand paper after each coat for better charge dissipation.
-
Mix all the three components provided in kit thoroughly for at least 2minutes. Mixture is then directly poured and spread with the help of trowel.
-
Allow 5-6 hour for surface to dry and 24 hours to achieve full strength flooring.
MR. JO Floor-ASL2
Packaging: 11.25 KG
System Properties
- Color: Pigmented
- Pot life @25°C: 20-40 mins
- Mixing Ratio: 100:50:100 PBW
- Electrostatic dissipating properties
- Mixture consistency: Self levelling
- Thickness: 2mm
- Coverage: 3.2 kg/m2
Applications
- Data center
- Semiconductor fabrication industry
- Military & aerospace industries
- Antistatic flooring
How to use
-
The mixture should be applied on a clean and rough surface. For good results, it is required that the substrate is free from loose particles. Suitable degreasing agent should be used to remove any grease, oil or traces on the surface.
-
Repair the surface if damaged. Allow 2-3 hours for surface of repaired area to dry. Choose a suitable product from Jpoxy’s JO range of Adhesives for repairing.
-
Apply primer for better adhesion on substrate. Copper mesh is suggested to be laid before applying primer. Allow 4-5 hours for surface of repaired area to dry. Choose a suitable product from Jpoxy’s JO range of Primers. Rub the surface with sand paper after each coat for better charge dissipation.
-
Mix all the three components provided in kit thoroughly for at least 2minutes. Mixture is then directly poured and spread with the help of trowel.
-
Allow 5-6 hour for surface to dry and 24 hours to achieve full strength flooring.
MR. JO Floorkot-HB
Packaging: 6 KG
System Properties
- Color: Pigmented
- Pot life @25°C: 20-40 mins
- Mixing Ratio: 100:20 PBW
- Good mechanical properties
- Mixture consistency: Flowable liquid
- Coverage: 4 m2/kg/coat
- Optics: Opaque
Applications
- Food courts
- Restaurant
- Parking lot
How to use
-
Remove all dust and debris by physical and mechanical means, prior
to application of the product. surfaces should be freed from
laitance and dust by sand-blasting. In case sand-blasting is not
possible, thorough abrading with a hard wire brush should be
preferable. -
Repair the surface if damaged. Allow 2-3 hours for surface of
repaired area to dry. Choose a suitable product from Jpoxy’s JO
range of
Adhesives for
repairing. -
Apply primer for better adhesion on substrate. Allow 4-5 hours for
surface of repaired area to dry. Choose a suitable product from
Jpoxy’s JO range of
Primers. -
Mix the two components provided in kit thoroughly for at least 2minutes.
Apply the mix directly by pouring and spreading with the help of trowel. -
Allow 5-6 hour for surface to dry and 24 hours to achieve full strength
coating.
MR. JO Floorkot-CMR
System Properties
- Color: Pigmented
- Pot life @25°C: 20-40 mins
- Mixing Ratio: 100:20 PBW
- Good Chemical resistant
- Mixture consistency: Flowable liquid
- Coverage: 4 m2/kg/coat
- Optics: Opaque
Applications
- Area prone to chemical spillage
- Laboratory
- Industrial floors
- Area prone to oil spillage
How to use
-
Remove all dust and debris by physical and mechanical means, prior to
application of the product. surfaces should be freed from laitance and
dust by sand-blasting. In case sand-blasting is not possible, thorough
abrading with a hard wire brush should be preferable. -
Repair the surface if damaged. Allow 2-3 hours for surface of repaired
area to dry. Choose a suitable product from Jpoxy’s JO range of
Adhesives for
repairing. -
Apply primer for better adhesion on substrate. Allow 4-5 hours for
surface of repaired area to dry. Choose a suitable product from Jpoxy’s
JO range of
Primers. -
Mix the two components provided in kit thoroughly for at least 2minutes.
Apply the mix directly by pouring and spreading with the help of trowel. -
Allow 5-6 hour for surface to dry and 24 hours to achieve full strength
coating.
MR. JO Floorkot-YLW
System Properties
- Color: Yellow
- Pot life @25°C: 20-40 mins
- Mixing Ratio: 100:20 PBW
- Good mechanical properties
- Mixture consistency: Brush able liquid
- Coverage: 40 rmt/kg/coat for 3” wide
- Optics: Opaque
Applications
- Direction marking on concrete roads
- Work area marking in manufacturing facilities
- Vehicle parking area marking in parking lot
- Vehicle parking area marking in garage
How to use
-
Remove all dust and debris by physical and mechanical means, prior to
application of the product. surfaces should be freed from laitance and
dust by sand-blasting. In case sand-blasting is not possible, thorough
abrading with a hard wire brush should be preferable. -
Repair the surface if damaged. Allow 2-3 hours for surface of repaired
area to dry. Choose a suitable product from Jpoxy’s JO range of
Adhesives for
repairing. -
Apply primer for better adhesion on substrate. Allow 4-5 hours for
surface of repaired area to dry. Choose a suitable product from Jpoxy’s
JO range of
Primers. -
Mix all the two components of flooring kit thoroughly for at least
2minutes. Make marking with masking tape as per required width and apply
the mix directly by brush or roller with in the marking. -
Allow 5-6 hour for surface to dry and 24 hours to achieve full strength
coating.
MR. JO Floorkot-CLR
System Properties
- Color: Clear
- Pot life @25°C: 25-45 mins
- Mixing Ratio: 100:50 PBW
- High Clarity
- Mixture consistency: Flowable liquid
- Coverage: 4 m2/kg/coat
- Optics: Transparent
Applications
- Decorative clear coat
- 3D floors
- Protective coating
- Area prone to oil spillage
How to use
-
Remove all dust and debris by physical and mechanical means, prior to
application of the product. surfaces should be freed from laitance and
dust by sand-blasting. In case sand-blasting is not possible, thorough
abrading with a hard wire brush should be preferable. -
Repair the surface if damaged. Allow 2-3 hours for surface of repaired
area to dry. Choose a suitable product from Jpoxy’s JO range of
Adhesives for
repairing. -
Apply primer for better adhesion on substrate. Allow 4-5 hours for
surface of repaired area to dry. Choose a suitable product from Jpoxy’s
JO range of
Primers. -
Mix all the two components provided in kit thoroughly for at least 2
minutes. Apply the mix directly by pouring and spreading with the help
of trowel. -
Allow 5-6 hour for surface to dry and 24 hours to achieve full strength
coating.
MR. JO Floorkot-AS
System Properties
- Color: Pigmented
- Pot life @25°C: 25-45 mins
- Mixing Ratio: 100:20 PBW
- Electrostatic dissipating properties
- Mixture consistency: Flowable liquid
- Coverage: 4 m2/kg/coat
- Optics: Opaque
Applications
- Data center
- Semiconductor fabrication industry
- Military & aerospace industries
- Antistatic coating
How to use
-
Remove all dust and debris by physical and mechanical means, prior to
application of the product. surfaces should be freed from laitance and
dust by sand-blasting. In case sand-blasting is not possible, thorough
abrading with a hard wire brush should be preferable. -
Repair the surface if damaged. Allow 2-3 hours for surface of repaired
area to dry. Choose a suitable product from Jpoxy’s JO range of
Adhesives for
repairing. -
Apply primer for better adhesion on substrate. Copper mesh is suggested
to be laid before applying primer. Allow 4-5 hours for surface of
repaired area to dry. Choose a suitable product from Jpoxy’s JO range of
Primers. Rub the surface with sand paper after each coat for better
charge dissipation -
Mix the two components provided in kit thoroughly for at least
2minutes. Apply the mix directly by pouring and spreading with the
help of trowel. -
Allow 5-6 hour for surface to dry and 24 hours to achieve full
strength coating.
MR. JO Primer-MVC
System Properties
- Color: Pale yellow
- Pot life @25°C: 120-150 mins
- Mixing Ratio: 100:50 PBW
- Mixture consistency: Medium viscosity liquid
- Coverage: 4 m2/kg
- Optics: : Transparent/Translucent
Applications
- Substrate pore sealing
- Adhesion promoter
- Sealer coat
How to use
-
Surfaces should be freed from laitance and dust by sand-blasting. In case sand-blasting is not possible, thorough abrading with a hard wire brush should be preferable. Suitable degreasing agent should be used to remove any grease, oil or traces on the surface.
-
Mix the two components together thoroughly for at least 2 minutes so as to achieve uniform mixing and thorough consistency of the mix. Apply the mix using brush or spatula to the pretreated surfaces.
-
Allow 4-5 hours for surface to dry and 24 hours to achieve full strength.
MR. JO Primer-LVC
System Properties
- Color: Pale yellow
- Pot life @25°C: 100-120 mins
- Mixing Ratio: 100:50 PBW
- Mixture consistency: Low viscosity liquid
- Coverage: 4 m2/kg
- Optics: Transparent/Translucent
Applications
- Sealing minute pinholes
- In between substrate & topcoat to enhance
- adhesion
- Structure strengthening
How to use
-
Surfaces should be freed from laitance and dust by sand-blasting. In
case sand-blasting is not possible, thorough abrading with a hard wire
brush should be preferable. Suitable degreasing agent should be used to
remove any grease, oil or traces on the surface. -
Mix the two components together thoroughly for at least 2 minutes so as
to achieve uniform mixing and thorough consistency of the mix. Apply the
mix using brush or spatula to the pretreated surfaces. -
Allow 4-5 hours for surface to dry and 24 hours to achieve full
strength.
MR. JO Primer-UPS
System Properties
- Color: Brownish
- Pot life @25°C: 80-100 mins
- Mixing Ratio: 100:50 PBW
- Mixture consistency: Medium viscosity liquid
- Damp, moist & underprepared substrate curing
- Coverage: 4 m2/kg
- Optics: Transparent/Translucent
Applications
- Concrete strengthening
- Adhesion promoter
- Sealer coat
How to use
-
The mixture should be applied on a clean and rough surface. For good
results, it is required that the substrate is free from loose particles.
Suitable degreasing agent should be used to remove any grease, oil or
traces on the surface. -
Mix the two components in small batches thoroughly for at least
2minutes. Apply the mix using brush or spatula to the pretreated
surfaces. -
Allow 4-5 hours for surface to dry and 24 hours to achieve full
strength.
MR. JO Primer-AS
System Properties
- Color: Black
- Pot life @25°C: 90-120 mins
- Mixing Ratio: 100:30 PBW
- Mixture consistency: Thixotropic paste
- Electrostatic dissipating properties
- Coverage: 4 m2/kg
- Optics: Opaque
Applications
- Data center
- Semiconductor fabrication industry
- Military & aerospace industries
- Antistatic coating
How to use
-
Surfaces should be freed from laitance and dust by sand-blasting. In
case sand-blasting is not possible, thorough abrading with a hard wire
brush should be preferable. Suitable degreasing agent should be used to
remove any grease, oil or traces on the surface. -
Mix the two components together thoroughly for at least 2 minutes so as
to achieve uniform mixing and thorough consistency of the mix. . Copper
mesh is suggested to be laid before applying primer. Apply the mix using
brush or spatula to the pretreated surfaces. -
Allow 4-5 hours for surface to dry and 24 hours to achieve full
strength. Rub the surface with sand paper after each coat for better
charge dissipation.
MR. JO Underlay-TMP
System Properties
- Color: Neutral
- Pot life @25°C: 120-150 mins
- Mixing Ratio: 100:50:650 PBW
- Mixture consistency: Tampable
- Coverage: 1.8 kg/m2/mm
Applications
- Flooring
- Pavement
- Slope for drainage
- As a bedding to enhanced floor’s mechanical strength
How to use
-
Remove all dust and debris by physical and mechanical means, prior to
application of the product. surfaces should be freed from laitance and
dust by sand-blasting. In case sand-blasting is not possible, thorough
abrading with a hard wire brush should be preferable. -
Repair the surface if damaged. Allow 2-3 hours for surface of repaired
area to dry. Choose a suitable product from Jpoxy’s JO range of
Adhesives for
repairing. -
Apply primer for better adhesion on substrate. Allow 4-5 hours for
surface of repaired area to dry. Choose a suitable product from Jpoxy’s
JO range of
Primers. -
Mix all the three components provided in kit thoroughly for at least
2minutes. Apply the mix directly by pouring and spreading with the help
of trowel. -
Allow 4-5 hour for surface to dry and 24 hours to achieve full strength
flooring.
MR. JO Underlay-FLO
System Properties
- Color: Neutral
- Pot life @25°C: 100-120 mins
- Mixing Ratio: 100:50:250 PBW
- Mixture consistency: Flowable
- Coverage: 1.8 kg/m2/mm
Applications
- Flooring
- Pavement
- Slope for drainage
- As a bedding to enhanced floor’s mechanical strength
How to use
-
Remove all dust and debris by physical and mechanical means, prior to
application of the product. surfaces should be freed from laitance and
dust by sand-blasting. In case sand-blasting is not possible, thorough
abrading with a hard wire brush should be preferable. -
Repair the surface if damaged. Allow 2-3 hours for surface of repaired
area to dry. Choose a suitable product from Jpoxy’s JO range of
Adhesives for
repairing. -
Apply primer for better adhesion on substrate. Allow 4-5 hours for
surface of repaired area to dry. Choose a suitable product from Jpoxy’s
JO range of
Primers. -
Mix all the three components provided in kit thoroughly for at least
2minutes. Apply the mix directly by pouring and spreading with the help
of trowel. -
Allow 4-5 hour for surface to dry and 24 hours to achieve full strength
flooring.
MR. JO Underlay-CMR
System Properties
- Color: Neutral
- Pot life @25°C: 80-100 mins
- Mixing Ratio: 100:60:650 PBW
- Mixture consistency: Tampable
- Good chemical resistant
- Coverage: 1.8 kg/m2/mm
Applications
- Industrial flooring
- Pavement
- Slope for drainage
- As a bedding to enhanced floor’s mechanical strength
How to use
-
Remove all dust and debris by physical and mechanical means, prior to
application of the product. surfaces should be freed from laitance and
dust by sand-blasting. In case sand-blasting is not possible, thorough
abrading with a hard wire brush should be preferable. -
Repair the surface if damaged. Allow 2-3 hours for surface of repaired
area to dry. Choose a suitable product from Jpoxy’s JO range of
Adhesives for
repairing. -
Apply primer for better adhesion on substrate. Allow 4-5 hours for
surface of repaired area to dry. Choose a suitable product from Jpoxy’s
JO range of
Primers. -
Mix all the three components provided in kit thoroughly for at least
2minutes. Apply the mix directly by pouring and spreading with the help
of trowel. -
Allow 4-5 hour for surface to dry and 24 hours to achieve full strength
flooring.